Specifications
Dimplex Thermal Solutions 1800-YOU-KOOL       
PRE-STARTUP PROCEDURE: 
1.  Complete all steps of the installation process 
before applying power to the chiller. 
2.  If the unit is equipped, ensure the system 
switch is in the OFF position, then turn on the 
main power disconnect. The temperature 
controller will turn on and automatically go into 
a self-test. When the self-test is complete, the 
controller will begin to monitor the process 
fluid. 
3.  For units that run on three-phase power, 
motor rotation must be checked and 
corrected to  avoid damaging the chiller 
and voiding the warranty. If the chiller is 
equipped with a phase protector, the unit will 
not start up and may display a fault if phase 
rotation is not correct. Correcting phase 
rotation should make this fault go away. 
  Single phase units will not be affected by any 
certain phase rotation and should continue on 
with step 4 of the pre-startup procedure. 
  If the unit is equipped with a process fluid 
pump, phase rotation can be checked by briefly 
turning on the system and allowing the pump 
to energize. Watch the rotation of the cooling 
fan on the pump to see that it is turning in the 
direction indicated by the rotation arrow on the 
pump motor. Do not use condenser fans to 
judge phase rotation as many three phase 
units have single phase fans and will run 
correctly from DTS even with incorrect power 
phasing. 
If the unit does not have a pump or any other 
visual method of checking rotation, a phase 
checking device can be used to check power at 
the disconnect. All components of the chiller 
are wired to operate with a “right-hand” phase 
rotation. If you do not have a phase checking 
device, a certified refrigeration technician 
should be utilized to monitor refrigerant 
pressures as the chiller compressor comes 
online. 
All motors within the chiller are 
synchronized at the factory for proper 
rotation. If one motor is turning in the wrong 
direction, all other motors will as well. DO 
NOT change the orientation of any motor leads 
within the chiller. If phase rotation is incorrect, 
shut off the power feed and change any two 
incoming power leads BEFORE the main 
disconnect. 
4.  Chillers two tons or larger are equipped with a 
compressor crankcase heater. These units 
must have power supplied to the unit with only 
the disconnect switch on for 8 hours prior to 
starting the chiller. This will raise the 
temperature of the compressor oil 
enough to vaporize any refrigerant 
that may be in the crankcase oil.  
Failure to allow this warm-up 
can result in compressor damage. 
5.  Ensure all process fluid lines and shutoff valves 
are open and the system is able to flow freely.  
Re-check the fluid level in the system before 
continuing with the startup. 
INITIAL STARTUP & OPERATING 
PROCEDURE: 
1.  Complete all steps of the pre-startup procedure 
before starting the chiller process. 
2.  Before turning on the chiller system, become 
familiar with the operation of the temperature 
controller on the chiller. Refer to the 
temperature controller guide in this manual for 
instructions. 
3.  Turn on the chiller process by moving the 
selector switch to either ON or LOCAL. If the 
unit is wired to start remotely, turn the selector 
switch to REMOTE and start the chiller from the 
other location. 
  Chillers that do not have a process selector 
switch or remote control should begin the 
chilling process as soon as the disconnect 
switch is turned on. 
4.  If the unit is equipped with a process pump, it 
will energize and produce flow as soon as the 
chiller is turned on.  Monitor any system 