Installation guide
Unpacking the DECarray
3.5 Inspecting the DECarray Cabinet
3.5 Inspecting the DECarray Cabinet
Inspect the DECarray cabinet first from the front, then from the rear.
1. Open the front and rear cabinet doors.
a. Turn the two hex-Allen fasteners at the right edge of each door
counterclockwise to unlock them.
b. For each door, grasp the door by its edge, and pull toward you.
2. Verify that all operator control panels are correctly seated on each
SF-series storage enclosure installed in the cabinet.
WARNING
Adhere to electrostatic discharge (ESD) procedures at all times. Use
the ESD straps available with every storage array.
3. At the rear of the DECarray cabinet, check the serial/logo label to verify
that the correct voltage variation of the power controller exists to meet the
power supplied to the installation site (Figure 3–8).
4. Ensure that all ac power cords going to the power controller from devices
installed in the storage array are correctly seated in the power controller.
5. Ensure that the ac breaker is off (Figure 3–8).
6. Ensure that the bus switch of the power controller is in the on (down)
position (Figure 3–8).
Unpacking the DECarray 3–11