Installation guide

Installing an SF200 Storage Array with a VAX 6000 Series System 4–47
4.4.4 Powering Up the SF200 Storage Array (Dual-Host)
Now that the SF200 storage array has been installed and labeled, you are
ready to apply power. Follow the steps in order.
CAUTION
Ensure that the ac power switch on each SF72 storage enclosure
and magazine tape subsystem installed is in the off position.
1. At the rear of the storage array, turn the 881 power controller on
(Figure 4–24). Ensure that the BUS/OFF/ON switch is in the down
position.
J10
J11
J12
J13
I
CB
O
FUSE
LABEL
CIRCUIT
BREAKER
POWER CORD
STRAIN RELIEF
GROMMETED
CORD
OPENING
POWER CONTROL
BUS CONNECTORS
POWER
CORD
FUSE
BUS/OFF/ON SWITCH
(SYMBOLS CLOCKWISE FROM TOP)
UNDELAYED
DELAYED
(0.5 SEC)
SERIAL/LOGO
LABEL
881
SHR-X0107-90
Figure 4–24 881 Circuit Breaker