Installation guide
Installing an SF200 Storage Array with a VAX 6000 Series System 4–29
4.3.5 Single-Host Final Verification
Now that all the hardware installation, cabling and labeling, and the
powering up steps are complete, you are ready to configure the DSSI
subsystem and verify the correct operation of each ISE in the array with
the host system.
Refer to the KFMSA Module Installation and User Manual (EK–KFMSA–
IM) and the TF837 Magazine Tape Subsystem Service Manual (EK–
TF837–SM) for detailed information and how to proceed with verifying the
correct operation of each ISE that has been installed. In these manuals,
you will find the procedure for establishing the communications between
the ISEs, the adapter module, and the system. You will also find the step-
by-step procedures for reconfiguring the system with its newly installed
DSSI devices.
Refer to the manuals for the disk ISE and tape ISE for detailed
information on the local programs in the ISEs.
Remember, each SF72 enclosure can contain two or four disk ISEs. Each
magazine tape subsystem contains one tape ISE. A fully configured
storage array contains 24 disk ISEs and 2 tape ISEs.
If at any time you detect a failure, refer to Chapter 7.
Once the verification is complete, close the cabinet doors; turn the hex-
Allen fasteners one quarter turn clockwise to lock. The system is ready to
be turned over to the system manager.