Installation guide
Installing the Magazine Tape Subsystem in an SF200 Storage Array 6–41
6.3 Powering Up the Magazine Tape Subsystem
Follow these steps to apply power to a newly install SF72 storage
enclosure.
1. Turn the ac power switch on the rear of the subsystem on or to the "1"
position.
After you power on the TF837 magazine tape subsystem,
1. All its OCP indicators turn on (generally within 15 seconds.)
2. While the elevator scans the magazine, all OCP indicators, except
for Power On, turn off
3. Assuming the subsystem has a magazine with a cartridge in
position 0, and there’s no cartridge in the drive, the final power-on
self-test status displayed
a. Power On indicator on
b. Eject indicator on
c. Load/Unload indicator on
d. Position Select indicator on
e. Position 0 indicator on.
2. Should a fault occur, refer to Chapter 7 or the TF837 Magazine Tape
Subsystem Service Manual (EK–TF837–SM).
Once these steps are accomplished and the subsystem has passed POST,
then proceed to the next section.
6.3.1 Updating the System Configuration Sheet
Now that the subsystem has been successfully installed, power has been
applied, and the drives have passed POST, you are ready to update the
system configuration sheet.
Refer to the KFMSA Module Installation and User Manual (EK–KFMSA–
IM) for complete details on how to fill out a system configuration sheet.