User's Manual

©DeltaNode Solutions 2015
4
Revision 15-01
Warning!
It is NOT recommendable to use markets unknown manufacturers for the passive
components within the DAS. Before using the passive components, the datasheets of such
components should be revised closely by the responsible network provider and all link
budgeting calculations should be done accordingly.
2.2 Installing the Master Unit
All equipment must be properly grounded. This means that the ground peg in the mains connector
for both head-end gear (Master Unit) and remote gear (Remote Units) must be connected to Phase,
Neutral and Ground in a proper way before the plug is inserted in the unit.
The chassis of the remote and the rack of the master unit should be grounded to a potential bar or
safety grounding bar when operated. All electrical installations should be done by an FCC Licensee
or/and a certified electrician only!
Figure1: Master Unit Frame (example1) Figure2: Master Unit Frame (example2)
Mount the BMU frames into cabinets
Mount ethernet switches and cables
Mount power cables (use P101 on the frames for primary power, P102 for secondary power)
Install BGW and connect cables
Insert all units
Start switches
Start BGW, wait for a few minutes until it comes up and log into it to start optimizing the
system