Installation manual

77
Operation and Installation Manual for SOLIVIA 2.0/2.5/3.0/3.3/3.6/5.0 EU G4 TR
12. Diagnostics and Troubleshooting
EN
12.5 Current Grid Settings
Menu 131 View Grid Setup
Description
The current grid settings can be displayed using 131 View Grid
Setup The contents of this menu are write-protected.
Accessing the Menu
Main Menu > Install Settings > Grid Selection > View Grid
Setup
Options
Install settings
-------------------
SOLIVIA ##
1. In the main menu, press the
buttons to select Install
Settings and then press the
button.
Display settings
Date and time
Language: English
Grid selection
RS485
100 Install settings
2. Press the buttons to
select Grid Selection and then
press the
button.
Grid change
View grid setup
-------------------
130 Grid selection
3. Press the buttons to
select View Grid Setup and
then press the
button.
Depending on the current
grid settings, different
messages may be dis-
played rst.
##.#W/##.#kVA
been limited to
of that inverter has
The maximum power
activated
Power balancing is
4. When the messages are dis-
played, press the
button to
conrm each.
Fnom: 50.00Hz
Grid: DE LVD
--------------------
131 View grid setup
5. You can view the whole list by
pressing the
buttons.
12.6 Autotest for Italy
Menu 610 IT Autotest
Description
NOTE
The "Italy Autotest" is only available when the
grid has been set to IT BT 21 < 6 kW.
In accordance with the CEI 0-21:2012-06 standard, an autotest is
required for PV systems equal to or less than 6 kW.
The autotest is performed during commissioning when the grid is
set to IT. BT 21 < 6kW. The autotest can then be performed at any
time.
The Autotest checks the proper operation of the grid and system
protection.
The solar inverter may only be put into operation when the test
result of the last autotest is Pass. The reports for the last ve
autotests are saved.
During the autotest, all parameters required in CEI 0-21 on the AC
side of the solar inverter are tested.
Once the autotest is complete, the result is displayed (see Table
12.3, p. 78). The overall result is "Pass" only when all subtests
have been passed.
Performing Autotest
Main Menu > Diagnostic&Alarm > IT Autotest > Perform
Autotest
USB features
Options
Production info
Diagnostic&Alarm
Inverter info
SOLIVIA ##
1. In the main menu, press
the
buttons to select
Diagnostic&Alarm and then
press the
button.
AT Report 1
Perform autotest
-------------------
610 IT Autotest
2. Select Perform Autotest using
the
buttons, then press
the
button to perform the
autotest.
The autotest starts.
...test ongoing...
611 Perform autotest
3. The Autotest checks the proper
operation of the grid and sys-
tem protection.
The test result is displayed
after the autotest is com-
pleted.
IT-Grid: 00.01.00
12.08.2012 09:23:35
Result: Pass
612 AT Report 1
4. You can view the whole list by
pressing the
buttons.