8. Commissioning
Operation and Installation Manual for SOLIVIA 2.0/2.5/3.0/3.3/3.6/5.0 EU G4 TR
46
to reselect
ESC:
to confirm
ENTER:
17. Press the button to complete commissioning.
or
Press the
button to change settings.
þ Commissioning is now nished.
NOTE
► If the solar inverter is congured to the DE
LVD oder DK LVD grids, you can also con-
gure active and reactive power control, see
“10.9 Active Power Control”, p. 56.
► The solar inverter offers some optional
functions available for all grids, see “10 Set-
tings”, p. 52.
► When done with commissioning, save
the settings (see “11.4 Saving Settings”,
p. 65) and swap data (see “11.6 Saving
Swap Data”, p. 67) to a USB drive in
order to be able to use them later.