Reference Guide

Achieve high availability on Windows Server
2012/2016
The following are the steps to achieve high availability on Windows Server 2012/2016:
1 Add failover cluster feature on Windows Server 2012/2016—see Adding failover cluster feature on Windows Server 2012/2016.
2 Create le share witness—see Create le share witness.
3 Congure cluster Quorum—see Congure cluster Quorum.
4 Create clustered roles—see Create cluster roles.
Add failover cluster feature on Windows Server
2012/2016
About this task
To add the failover clustering feature on the Windows server 2012, do the following:
Steps
1 In Microsoft Windows Server 2012/2016, click Start to open the Start screen and then click Server Manager to launch the Server
Manager
dashboard.
NOTE
: Server Manager is a management console in Windows Server 2012/2016 that enables you to add server roles/
features, manage, and deploy servers.
2 Click Add roles and features and select an option to congure the server based on your requirement from the Add Roles and Feature
Wizard screen.
4
Achieve high availability on Windows Server 2012/2016 11