Deployment Guide
2
Install the Storage Center Hardware
This section describes how to unpack the Storage Center equipment, prepare for the installation, and mount the equipment in a
rack.
Unpack and Inventory the Storage Center Equipment
Unpack the storage system and identify the items in your shipment.
Figure 23. SCv2000/SCv2020 Storage System Components
1.
Documentation 2. Storage system
3. Rack rails 4. Front bezel
Prepare the Installation Environment
Make sure that the environment is ready for installing the Storage Center.
• Rack Space — The rack must have enough space to accommodate the storage system chassis, expansion enclosures, and
switches.
• Power — Power must be available in the rack, and the power delivery system must meet the requirements of the Storage
Center.
• Connectivity — The rack must be wired for connectivity to the management network and any networks that carry front-end
I/O from the Storage Center to servers.
Safety Precautions
Always follow these safety precautions to avoid injury and damage to Storage Center equipment.
If equipment described in this section is used in a manner not specified by Dell, the protection provided by the equipment could be
impaired. For your safety and protection, observe the rules described in the following sections.
NOTE: See the safety and regulatory information that shipped with each Storage Center component. Warranty
information is included within this document or as a separate document.
Installation Safety Precautions
Follow these safety precautions: