Setup Guide

Two-post ush-mount conguration
NOTE: Your system is not NEBS Earthquake Z4-compliant if you use this installation
method.
1 For this conguration, remove the latch castings from the front side of each ReadyRails
assembly, item 1.
To remove the two screws and latch casting from each front ange ear, on the switch
side of the rail, use a Torx driver. Retain the castings for future rack requirements. It is
not necessary to remove the rear ange castings.
2 Attach one rail to the front post ange with two user-supplied screws, item 2.
3 Slide the plunger bracket forward against the vertical post and secure the plunger
bracket to the post ange with two user-supplied screws, item 3.
4 Repeat this procedure for the second rail.
Hardware installation 13