Install Guide
Table Of Contents
- Dell EMC PowerSwitch S3048-ON Installation Guide March 2021
- About this guide
- The S3048–ON switch
- Site preparations
- NEBS compliance
- Install the S3048–ON
- Power supplies
- Fans
- Management ports
- Specifications
- Chassis physical design
- IEEE Standards
- Agency compliance
- USA Federal Communications Commission Statement
- European Union EMC Directive Conformance Statement
- Japan VCCI Compliance for Class A Equipment
- Korean Certification of Compliance
- Safety Standards and Compliance Agency Certifications
- Electromagnetic compatibility
- Product recycling and disposal
- Dell EMC support
3. Slide the plunger bracket forward against the vertical post and secure the plunger bracket to the post flange with two
user-supplied screws. item 3.
4. Repeat this procedure for the second rail.
Two-post center-mount installation
1. Slide the plunger bracket rearward until it clicks into place and secure the bracket to the front post flange with two
user-supplied screws, item 1.
Figure 7. Two-post center-mount configuration
2. Slide the back bracket towards the post. Secure it to the post flange with two user-supplied screws, to item 2.
3. Repeat this procedure for the second rail.
Four-post threaded installation
1. For this configuration, remove the flange ear castings from each end of the ReadyRails assemblies.
To remove the two screws from each flange ear and remove each casting, use a Torx driver, item 1. Retain the castings for
future rack requirements.