Replacement Procedure

8 Control Processor Blade (CP8) Replacement Procedure
53-1001806-01
7. Verify the installation (“Verifying operation of the new CP blade”).
8. Replace the chassis door (see the Chassis Door Replacement Procedure for your chassis).
9. Remain logged in to the active CP and continue to “Verifying operation of the new CP blade.”
Verifying operation of the new CP blade
ATTENTION
The instructions below reference specific slot numbers. these numbers will be different between the PowerConnect
B-DCX-4S and PowerConnect B-DCX.
To verify that boot and POST are complete on the new CP blade and that the CP blade has achieved failover
redundancy, perform the following steps.
1. Type slotShow. The command output shows the new CP blade as “enabled”:
rsl8-st03-dcx-1:admin> slotShow
Slot Blade Type ID Status
---------------------------------
1 SW BLADE 16 ENABLED
2 SW BLADE 16 ENABLED
3 SW BLADE 16 ENABLED
4 SW BLADE 16 ENABLED
5 CR BLADE 17 ENABLED
6 CP BLADE 18 ENABLED
7 CP BLADE 18 ENABLED
8 CR BLADE 17 ENABLED
9 SW BLADE 16 ENABLED
10 SW BLADE 16 ENABLED
11 SW BLADE 16 ENABLED
12 SW BLADE 16 ENABLED
rsl8-st03-dcx-1:admin>
2. Determine the version by typing firmwareShow.
This example shows sample output for the firmwareShow command:
rsl8-st03-dcx-1:admin> firmwareShow
Slot Name Appl Primary/Secondary Versions Status
--------------------------------------------------------------------------
2 FS8-18 FOS v6.1.0
v6.1.0
4 FR4-18i FOS v6.1.0
v6.1.0
6 CP0 FOS v6.1.0 ACTIVE *
v6.1.0
Co-FOS v6.1.0
v6.1.0
7 CP1 FOS v6.1.0 STANDBY
v6.1.0
Co-FOS v6.1.0
v6.1.0