Installation guide
24 | Install the S6000
www.dell.com | support.dell.com
Configuring a Two-Post Flush-Mount
Step Task
1 For this configuration, remove the castings from the front side of each ReadyRails assembly. Refer to
Figure 4-2
,
item 1. To remove the two screws from each front flange ear (on the switch side of the rail) and remove each
casting, use a Torx driver. Retain the castings for future rack requirements. It is not necessary to remove the rear
flange castings.
Figure 4-2. Two-Post Flush-Mount Configuration
2 Attach one rail to the front post flange with two user-supplied screws. Refer to
Figure 4-2
, item 2.
3 Slide the plunger bracket forward against the vertical post and secure the plunger bracket to the post flange with
two user-supplied screws. Refer to
Figure 4-2
, item 3.
4 Repeat this procedure for the second rail.