Setup Guide

4 Repeat this procedure for the second rail.
Figure 26. Installing the Switch using a Two-Post Flush-Mount Configuration
Configuring a Two-Post Center-Mount
To install your switch in a two-post center-mount configuration, follow these steps.
1 Slide the plunger bracket rearward until it clicks into place and secure the bracket to the front post flange with two user-
supplied screws. See item 1 in the following illustration.
2 Slide the back bracket towards the post and secure it to the post flange with two user-supplied screws. See item 2 in the
following illustration.
Install a S3100 Series System 36