Install Guide

PS6210 Install and Setup Guide
3 Connecting the Array Cables
Turning On the Array
Beforeturningonpower,allowsufficienttimeforthearraytoadjusttoambienttemperature(forexample,
overnight).
Note: Youcanturnonthepowertoonepowersupplyfirst(eitherone),orbothatthesametime.
1. Findthepowerswitch,locatedeitherbelowthepowerplugona2Uarrayorabovethepowerplugona4U
array.SeeFigure8andFigure9.
2. PressthepowerswitchtotheONposition.Thepowerindicatorswilllight.
Batterieswillstarttochargeandsomehardwarecomponentswillstarttosynchronize.LEDswillindicatethese
normalactivities.Thebatterybackupunitinstalledineachcontrollerisshippedinapartiallydischargedstate.
Thefirsttimethesystemispoweredon,abootdelayofupto30minutesmightbeexperiencedwhilethebattery
ischargedtofullcapacity.
Figure 8: AC Power Supply Switch and LEDs (2U Array)
Figure 9: AC Power Supply Switch and LEDs (4U Array)
13