Unit installation

Pre-Start
74 SCXF-SVX01K-EN
Units with Electric Heat
Verify the supply air temperature sensor is
downstream of the electric heat coil.
Electrical
Verify electrical connections are tight.
Components
Verify liquid line service valve, and suction and
discharge service valves if present, are open at startup.
Note: Eac
h compressor suction line contains a low
pressure sensor that will shut the compressor
down in low pressure situations. See Table 36,
p. 56.
Ensure system components are properly set and
installed.
Note: Thermal
expansion valve superheat is factory set
and requires no field adjustment. Operating
superheat should be between 14-20°F. Actual
superheat depends on several factors (operating
conditions, system load step, system charge,
piping and condenser head pressure control.)