2
DR
A
FT
PREPARING FOR INSTALLATION
This chapter explains how to prepare to install the SkyZhone 45 system, and
includes the following sections:
• Site selection requirements, page 19
• Antenna path guidelines, page 19
• Received Signal Level and link budget, page 20
• Fade margin calculations, page 21
• Unit Frequencies, page 21
• Powering the units, page 21
• Equipment, page 22
Site selection requirements
The performance of the SkyZhone 45 system depends upon its proper
installation. A good installation conforms to these guidelines:
• The antennas are installed in line-of-sight of each other, with adequate
clearance.
• The antennas are mounted to stable structures.
• There is dependable, protected and easily accessible power at each site.
• The coaxial connection between the IDU and ODU is no longer than 300
ft.
Antenna path guidelines
The SkyZhone 45 wireless transport will not operate properly unless you can
see each antenna from the other. High frequencies used cannot pass through
trees or other obstacles. In general, consider the following when calculating
line-of-site between the antennas:
• The curvature of the earth.
• Buildings and trees.
• Future tree growth and construction.