Full Product Manual

11
IMPORTANT
The D-12A Alignment Lift MUST be installed in the configuration shown in Figure 1.
For the D-12 ONLY, the power unit can be located at either "X" locations shown in Figure 1 or 2. It is important to locate
the POWERSIDE runway (with cylinder) on the SAME SIDE as the power unit location. Utility rails on the side of each
runway MUST be installed to the inside. NOTE: In order to change the location of the power unit, the cross tubes and
the powerside runway must be reversed.
Fig 2
Fig 1
POWER UNIT LOCATION
Power Unit X
X Power Unit
Powerside Runway
Powerside Runway