STEP 5
(Install Offside Column)
1. Position the OFFSIDE column at the designated chalk locations and secure to the floor following the
same procedures as outlined in STEP 4.
STEP 6
(Mounting the Top Pulley Assembly)
1. Position the top pulley plate on top of the columns. Bolt to the columns using the M10 x 40mm Hex
Bolts, Nuts and Washers. ( See figure 6 )
STEP 7
(Mounting the Power Unit)
1. Attach the power unit and vibration pad to the powerside column using four M8 x 25mm hex bolts and
nylon lock nuts supplied (See Fig. 7). Fill the reservoir with 12 quarts Aw-32 hydraulic oil or Dexron III
or VI transmission fluid . Be sure to use a clean funnel.
STEP 8
( Installing Equalizer Cables)
1. Raise and lock each carriage approximately 28" above the ground.
2. Make sure that the safety locks on each column are fully engaged before attempting to route equalizer
cables. Carriages must be equal height from the floor before proceeding. Failure to assure lifting car-
riage is on the lock may result in rapid drop causing severe injury.
Fig: 6
Fig: 7
DANGER