Field line connection: Control wiring and cool/heat selection
See figure 10.
Setting the cool/heat operation
1 Performing cool/heat setting with the remote controller
connected to the indoor unit.
Keep the cool/heat selector switch (DS1-1) on the outdoor unit
PC board at the factory setting position IN/D UNIT. (See
figure 11).
2 Performing cool/heat setting with the cool/heat selector.
Connect the cool/heat selector remote controller (optional) to the
A/B/C terminals and set the cool/heat selector switch (DS1-1) on
the outdoor unit PC board to OUT/D UNIT. (See figure 12).
■ The wiring from the indoor units must be connected to the F1/F2
(In-Out) terminals on the PC board in the outdoor unit.
■ After installing the interconnecting wires inside the unit, wrap
them along with the on-site refrigerant pipes using finishing
tape, as shown in figure 14.
For the above wiring, always use vinyl cords with 0.75 to 1.25 mm
2
sheath or cables (2-core wires). (3-core wire cables are allowable for
the cooler/heater changeover remote controller only.)
Precautions when laying power wiring
Use round pressure terminals for connections to the power
terminal block.
When none are available, follow the instructions below.
■ Do not connect wiring of different thicknesses to the
power terminal block. (Slack in the power wiring may
cause abnormal heat.)
■ When connecting wiring which is the same thickness,
do as shown in the figure below.
■ For wiring, use the designated power wire and
connect firmly, then secure to prevent outside
pressure being exerted on the terminal board.
■ Use an appropriate screwdriver for tightening the
terminal screws. A screwdriver with a small head will
strip the head and make proper tightening impossible.
■ Over-tightening the terminal screws may break them.
■ See the table below for tightening torque for the
terminal screws.
If an excessive force is applied while connecting a cable to
the terminal block on the PC board, the PC board may be
damaged.
1 Cool/heat selector
2 Outdoor unit PC board
3 Take care of the polarity
4 Use the conductor of sheathed wire (2 wire) (no polarity)
5 Ter minal board (field supply)
1 Remote controller
1 Cool/heat selector
NOTE
When the cool/heat selector is set to heat, you
cannot select cooling with the remote controller.
12
1 Round pressure terminal
2 Power wire
Tightening torque (N•m)
M5 (Power terminal block/ground wire) 2.39~2.92
M4 (Shielded ground) 1.18~1.44
M3.5 (Control wiring block) 0.79~0.97
For low-noise operation or demand operation, it is
necessary to get the optional 'External control adaptor for
outdoor unit' (DTA104A61/62).
For details, see the installation manual attached to the
adaptor.
■ Be sure to follow the limits below. If the unit-to-unit
cables are beyond these limits, it may result in
malfunction of transmission.
Maximum wiring length: 300 m
Total wiring length: 600 m
Maximum No. of branches: 9
■ Up to 9 branches are possible for unit-to unit cabling.
No branching is allowed after branching. (See
figure 13).
■ Never connect the power supply to unit-to-unit cabling
terminal block. Otherwise the entire system may
break down.
1 Liquid pipe
2 Gas pipe
3 Interconnecting wiring
4 Insulator
5 Finishing tape
1 Branch
2 Subbranching