Specifications
Power Train Testing and Adjusting
56
8. Install bearing nuts for correct bridge position and
lightly torque them to achieve bearing preload.
9. Tap on differential on both sides to achieve correct
bearing cone position, rotate differential (3-5 times).
10. Check drag 19.6 N.m (14.5 lb.ft) on rotating
differential.
11. When drag is correct, mark position of nuts both on
nuts and bridge.
12. After marking of position remove differential assy.










