Installation manual
4-2010 3. Step-By-Step Outline of Installation
Callout Component
Number
12 Fuel Connection (Female) 3/4 NPT & NG & LPV
13 4x Anchoring Spike
FIGURE 12. FUEL LINE CONNECTIONS
3.7.2 Fuel Line Connections (Model 14GSBB-6716A Only)
An Australian Gas Association (AGA) approved shutoff valve must be installed prior to generator
set installation in Australia or New Zealand. Adaptation from NPT to BSPT may be required,
depending on the valve used. The maximum amperage of the valve selected must be less than
1.0 amp at 12 VDC.
3.7.3 Natural Gas Fuel System
The generator set requires an adequate fuel supply to operate correctly at full load. The length
of the fuel supply pipe from the gas service entrance to the generator set must be known to
determine the correct fuel pipe size. Refer to the Natural Gas Pipe Capacity - Cubic Feet of Gas
Per Hour table, located within the Natural Gas Supply Line Sizesection of this manual to find
the fuel supply requirement for your generator set. The Pipe must be a minimum of schedule 40
subject to the authority having jurisdiction.
3.7.3.1 Natural Gas Supply
NOTE: The Natural Gas supply meter may need to be exchanged for a higher
capacity meter to supply the additional gas consumed by the generator set.
A029V088 (Issue 2) 27