Technical data
58
CTC EcoZenith i250 
Installation
12. Pipe installation
The installation must be carried out in accordance with current standards 
and regulations. Refer to the Warm and Hot Water Installation Instructions 
1993. The product must be connected to an expansion vessel in an open or 
closed system. 
Do not forget to flush the radiator system clean before connection. 
Apply all the installation settings based on the description in the chapter 
“First start”.
12.1  Filling
Filling valve (no. 90, see schematic diagram on next page) is connected 
to the radiator return pipe. Alternatively, the valve can be installed in the 
direction of the expansion pipe. When the boiler and system are being filled 
with water, the mixing valve (Y1) must be fully open. Pull out the knob on the 
valve and turn it anticlockwise as far as you can. Do not forget to push and 
set the knob on the valve to automatic mode after filling. 
If the heat pump is not connected, connections 1 and 2 must be capped 
when filling with water. (See figure)
12.1.1 Pressure drop in mixing valve
The diagram below shows a drop in pressure in the mixing valve. 
Start with the heat requirement in kW (e.g. 15kW), then move vertically 
to the selected ∆t(e.g. 10°C). Then move horizontally to the line for the 
EcoZenith i250 mixing valve = line6.3DN20. The reading for the pressure 
drop is taken from the scale directly below (4 kPa).For EcoZenith i250, see 
valve DN20. 