C. If the work is delayed through the fault of the District (or of any separate contractor
employed by the District or of any condition by the District beyond the Contractor's
control) the schedule may be extended within a period agreed upon by the District and
the Contractor.
1. The Contractor shall notify the District, in writing, of any condition or situation that
in the Contractor's opinion warrants an extension of Contract Time.
2. The Contractor shall not be entitled to additional compensation or damages due to
delays, interference’s or interruptions to the Work or the Project, but shall be
entitled only to an appropriate extension of time in accord with the General
Conditions of the Contract for Construction.
PART 5 DEFICIENT WORK
5.01 PRODUCT AND INSTALLATION DEFICIENCIES
A. The Contractor shall expediently correct all deficiencies brought to his attention in writing
by the District. If, in the opinion of the District and the independent agency, the
Contractor fails to correct deficiencies, or fails to act expeditiously to correct deficiencies,
the District may:
1. Accept the deficiencies in the Work, and reduce the Contract Sum of the
Contractor at fault by a unilateral Change Order issued and signed by the District
in an amount to be determined by the District,
2. Have the deficiencies removed in any reasonable manner available to the District,
and charge the Contractor at fault for the costs incurred, or reduce that
Contractor's Contract Sum by a unilateral Change Order issued by the District for
the costs incurred.
B. The Contractor shall pay all costs of the Work including, but not limited to, labor,
materials, equipment, tools, transportation, freight, taxes, royalties, patent fees, support
facilities, construction equipment, water, heat, utilities, supervision, overhead, and all
other items necessary for the proper execution and completion of the Work.
PART 6 GENERAL
6.01 LEGAL REQUIREMENTS
A. The Contractor shall comply fully with all laws, statutes, ordinances, rules, regulations,
codes, and lawful orders applicable to their work, including employment regulations,
unless specifically exempted from compliance by the Contract Documents. Where local
codes differ from codes of broader jurisdictions, the more stringent code shall apply. The
Contractor shall promptly notify the District in writing of items in the plans or
specifications for this project that violate any applicable codes.
6.02 CLEAN SITE
A. The contractor shall clean the site daily.
B. The contractor shall be responsible for disposal and removal from the site any and all
waste and debris generated from their work.
C. All dust or ceiling debris generated as part of the work shall be cleaned each day.
6.03 PREVAILING WAGE
A. This project is subject to the Prevailing Wage Law; Michigan Public Act 166 of 1965.
6.04 TAXES
A. The bidder is responsible to apply all tax information within their proposal. Contractor is
responsible for applying such tax with each request for payment and complying with