Specifications
Technology Upgrade Front End 28 0500-7
1224_01
products.
B. The contractor shall be liable for all equipment until it is formally accepted by the owner
in writing. This shall include the equipment when it is in the contractor’s facility and when
it is in the owner’s facility until it is formally accepted.
3.04 DAMAGE
A. The contractor shall be responsible for all damage made to the building or any of the
buildings contents during their work as part of this project.
B. The contractor shall not disturb any hazardous material or materials that they are not
authorized to work with.
3.05 INCIDENTAL WORK AND PERMITS
A. The contractor shall be responsible for requesting, obtaining and paying for any and all
permits required for their work by the local, county, state and federal authorities having
jurisdiction (AHJ) over the work being performed.
B. Provide any and all work or equipment required by the Authority Having Jurisdiction
(AHJ) that may or may not be specifically noted in these documents.
3.06 INSPECTION OF THE WORK
A. The contractor shall keep up to date as-builts on site for the duration of the project. The
engineer may request to see the as-built documents at any time.
B. The Contractor shall promptly facilitate inspection and testing of the Work regardless of
expense as necessary or as requested by the District, regardless of whether or not the
Work in question is his own or that of a subcontractor.
C. If such tests or inspections reveal deficiencies as measured by Construction documents
or an independent consultant/testing agency or the owner/engineer, the Contractor shall
bear all costs incurred to correct such deficiencies, and the cost to reconstruct any work
to meet the contract documents.
3.07 PROJECT MEETINGS
A. The contractor shall attend project meeting as designated by the owner or engineer.
Attendance is mandatory.
B. Meetings will be biweekly during primary installation.
PART 4 WORK SCHEDULES
4.01 PROJECT SCHEDULE
A. It is the intention of the District to take possession of the Work by the established
completion date or earlier, within the shortest time possible consistent with good
construction practices.
1. There are numerous schedules for the work as it is being completed as part of the
overall construction upgrades.
2. Work at the 4-12 building shall be completed by August 10
th
, 2015
3. Work at the K-4 building shall be completed by January 2016.
B. Upon award of the contract the contractor shall provide a complete schedule for their
work. This shall reference dates in the document and be coordinated with the schedule of
any other contractors.
1. Include start date
2. Products installed
3. Punch list work complete
4. Substantial Completion
5. Final Completion after system has been working for 30 days with no outages or