Technology Upgrade Communications Room 28 1100-3
1224_01
2. Electrical outlet strip shall have 5 duplex outlets.
3. Provide all attachment hardware required to securely attach the outlet strip to the
back of the vertical cable ladder. Refer to detailed drawings for location.
4. Install and test all outlets prior to project completion.
5. Provide Hubbell #PR10420 plugmold or equal outlet strip with attached cord and 3-
prong plug.
F. Four-post adjustable rack with front and back mounting rails.
1. Rack shall be adjustable for depths between 27 inches and 32 inches. Adjustment
shall be in increments of 1/2 inch.
2. Rack shall have universal mounting holes on the front and back rack rails
3. Rack shall be black in color.
4. Rack shall be Ortronics #OR 19-84-T4SDA2732 or equal.
G. Wall Mount Cabinet:
1. The wall mount cabinets shall be black in color.
2. Cabinets shall provide adjustable 19 inch rack mounting rails.
3. Each cabinet shall have a center swingout feature that allows access to the front and
back of equipment after it is installed in the cabinet.
4. Knockouts for different size conduits shall be provided on the top and bottom
of the cabinet.
5. Swing side of the cabinet shall be reversible.
6. Each cabinet shall be no less than 24 inches deep.
7. The 48 inch high cabinet shall be Great Lakes Case and Cabinet # GL48WS-PV.
8. Each cabinet shall be provided with the following hardware:
a. Plexiglas door with lock.
b. Dual fan assembly mounted in the top of the cabinet.
c. 6 position power strip with circuit breaker and surge suppressor.
d. 110 degree gravity door stop.
e. six, (6) casters.
H. Communications rack, 19 inches wide, 84 inches high. Black in color with 45 rack mounting
units (1.75 inches per RU), self-supporting.
1. Rack shall have holes to attach 6 inch wide vertical organizers.
2. Base shall have holes for attaching to the floor.
3. The rack shall be Ortronics No. 19-84-T2SD or approved equal.
4. Bond each rack and all parts of the cable ladder as 1 ground system. Use Erico
Eriflex woven copper grounding braids to attach racks and ladder. Erico No. 556700
or other lengths as required.
5. Equip communication racks with cable ladder system for cable support and routing.
Refer to
I. Install a wall rack for support of devices as shown on the drawings
1. Wall rack shall be Hubbell #HPWWMR24 or equal
PART 3 EXECUTION
3.01 EXAMINATION
A. Location of the communications infrastructure shall be finalized in the communications room
prior to installation.
B. Locate all equipment to be installed, and make certain that space is available for
maintenance and service during the life of the system.
C. If any changes from the drawings are required, the Contractor shall submit a proposed layout
of the communications room to the Engineer for approval prior to installation.
3.02 PREPARATION
A. Clean floor prior to installation of the communications racks.