Specifications
Technology Upgrade Training 28 7750-6
1224_01
5. The training shall include the simulation of calls the user might get during each day
utilizing one telephone set for every two employees.
6. Provide class space for the same number of telephones that are installed or
connected.
7. Provide and hand out a “Cheat sheet” to each use that describes typical actions that
the user will be required to complete for use of the telephone system and voice mail.
8. Include an additional day on site for training of users no less than three weeks after
initial training. This day shall be used to answer any additional questions that they
3.08 DATA NETWORK TRAINING
A. Data Network Training
1. The contractor shall provide administrator level training on the data network
equipment and connectivity. This shall include training on the network management
system.
2. Create a login for the administrator.
3. Demonstrate how to add a switch, remove a switch and how to view statistics on the
system as a whole and for individual ports.
4. Demonstrate how to login to each switch and control the different aspects
5. Demonstrate how to configure the switch.
6. Training shall be no less than 15 hours and shall be broken out over three separate
days.
a. The first training shall be at the time of implementation.
b. The second training shall be approximately four weeks after the system is
cutover.
c. The third training shall be setup for two months after initial implementation.
B. Wireless Network Training
1. The contractor shall provide administrator level training on the wireless data network
equipment and connectivity.
2. Demonstrate how the system works during configuration.
3. Review how to install and remove new access points.
4. Demonstrate how to review statistics for throughput and users on each access point.
5. Demonstrate how to optimize use of the network.
6. Training shall be no less than 15 hours and shall be broken out over three separate
days.
a. The first training shall be at the time of implementation.
b. The second training shall be approximately four weeks after the system is
cutover.
c. The third training shall be setup for two months after initial implementation.
C. The Contractor shall provide a syllabus detailing what will be discussed at each of the
training classes to the engineer and owner prior to training commencing.
END OF SECTION