Specifications

Technology Upgrade Testing 28 7700-9
1224_01
4. During the check-out meeting the Contractor shall demonstrate that each system
works as configured and as wanted by the Owner.
5. Only after the Owner and Engineer have decided that the system is working as per
the specifications and the Owner’s requirements will the cutover be allowed to occur.
5.03 CUTOVER TESTINGDATA NETWORK
A. During the cutover the Contractor shall test the system to make sure it is working as
designed.
1. Ensure connectivity between wide area connections, where applicable.
2. Once patch cables are installed, the contractor shall test that user PC’s can be
connected to the network and access all files, applications and the Internet.
3. The wireless network system shall be up and running and shall be configured to
connect employees, students and visitors. Security between the two systems shall be
such that the visitors do not have access to the district network.
4. As users begin to be added, the contractor shall test and ensure that they are able to
connect to any local servers, remote servers and the internet.
5. The contractor shall walk around the building and demonstrate that a wireless laptop
can connect to the wireless network at any location in the building.
5.04 POST-CUTOVER TESTINGDATA NETWORK
A. The Contractor shall schedule a Substantial Completion” meeting after cutover where all of
the features of the entire data communications system shall be demonstrated.
1. This meeting shall be scheduled for a time when the system has been cutover, is
working correctly and is under full usage load.
2. Prior to the meeting, the Contractor shall provide a checklist of all the features and
components of the data system. This checklist will contain all the items required to be
working for signoff to occur.
3. Provide the list to the Engineer for review prior to scheduling the meeting. The
Engineer will review the checklist and make sure all components of the system are
being reviewed.
4. Once the list is reviewed and approved by the Engineer, the “Substantial Completion”
meeting can be scheduled.
5. During the “Substantial Completion” meeting, each item on the checklist shall be
demonstrated to work as it was intended.
6. If, at the end of the meeting, the Engineer and Owner sign the checklist, then the
installation will be “Substantially Complete.”
B. After Substantial Completion there shall be a 30 day acceptance period. The acceptance
period shall be used to show that the system functions under a full load and provides reliable
communications services. The acceptance period cannot begin until the data network is
being used under full load.
1. After the Completion of the Acceptance Period, the installation will be deemed
complete, and the warranty period can begin.
2. During the acceptance period, the data network and all of its components shall work,
without interruption, as it was designed and configured.
3. If there is an outage or interruption in service due to a malfunction or misconfiguration
of the system, the 30 day acceptance period shall begin again after the malfunction or
configuration has been shown to be completely repaired.
C. During the 30 day acceptance period, the Contractor shall provide the as-built
documentation regarding the data network and all its interconnections. The as-built
documentation shall include:
1. Spreadsheet listing all components, part numbers, serial numbers, IP addresses,
VLANS and location of the equipment installed.
2. As-built drawings of the connectivity of different system elements, detailing which
cables are used to interconnect the different items.
3. As-built drawings of the rack layouts.
4. Locations of the wireless access points.
5. Configuration details of the system.