Pre-Commissioning
Before starting the commissioning process, verify the status of the equipment as follows:
Access Unit (A2)
1.Verify that the correct band-specific Active Combiner modules are installed.
2.Ensure the RF cables between the BTS and modules are connected as designed.
3.Ensure the fibers are connected to the proper optical ports as designed.
4.Check LED of Status and Optical ports.
Expansion Unit (EU-O/E2-O)
1.Ensure the optical transceivers are inserted and fibers are connected to the proper optical ports as designed.
2.Check LED of Status and Optical ports.
Remote Unit (M2RU)
1.Verify that the correct band-specific PA modules are installed.
2.Ensure the RF cables from each PA module are connected tightly (If using M2RU with external antennas).
3.Ensure the optical transceivers are inserted and fibers are connected to the proper optical ports as designed.
4.Check LED of Status and Optical ports.
Optical Indicator Descriptions
Each pair of optical interface indicators shows the operating status of an optical module, as shown in Figure 2.
Figure 1. Optical Indicator 1