Pre-Commissioning
Before starting the commissioning process, verify the status of the equipment as follows:
Access Unit (A2)
1Verify that the correct band-specific Active Combiner modules are installed.
2Ensure the RF cables between the BTS and modules are connected as designed.
3Ensure the fibers are connected to the proper optical ports as designed.
4Check LED of Status and Optical ports.
Expansion Unit (EU-O/E2-O)
1Ensure the optical transceivers are inserted and fibers are connected to the proper optical ports as designed.
2Check LED of Status and Optical ports.
Remote Unit (M2RU)
1Verify that the correct band-specific PA modules are installed.
2Ensure the RF cables from each PA module are connected tightly (If using M2RU with external antennas).
3Ensure the optical transceivers are inserted and fibers are connected to the proper optical ports as designed.
4Check LED of Status and Optical ports.
Optical Indicator Descriptions
Each pair of optical interface indicators shows the operating status of an optical module, as shown in Figure 2.
Figure 1. Optical Indicator 1