12  Configuration 
This chapter describes the recommended adjustment procedure for the ARGUS AM Floor 
System. 
12.1  General considerations 
•  Refer to chapter 3.1 (page 6) for noise sources and installation guidelines. 
•  Install the antenna(s) and Control Unit at the required location. 
•  Connect the antennas to the corresponding connectors on the Control Unit. 
•  Connect the power supply to the power input of the Control Unit 
•  Switch on the power supply → the power LED on the Control Unit board will light 
up 
•  Wait for about 10 seconds for the system to start up. 
12.2  Configuration settings 
Although the ARGUS AM Floor System comes pre-configured with factory settings, it is 
necessary to fine-tune this board for best performance in the specific environment it is 
installed in. 
The ARGUS AM Floor System must be configured through the Field Bus using a laptop 
and Cross Point Device Explorer software.  