Installation guide

Crestron Green Light Express
®
Power Switching Cabinet GLPX-SW-FT
Installation Guide DOC. 6886B Crestron Green Light Express
®
Power Switching Cabinet GLPX-SW-FT 15
Feed-Through and Load Wiring (Section A)
CAUTION: Bypass jumpers are provided on each output to allow testing and to protect the modules during
installation. The jumper shorts the L and SW terminals so that the load circuit is energized when the branch breaker
is on.
NOTE: Do not remove the bypass jumper until all feed and load wiring has been completed, and the circuits
have been tested for electrical faults.
NOTE: Use copper conductors only rated 75° C.
Wire Gauge and Torque Values
TERMINAL CONNECTOR MAX
WIRE RANGE
TORQUE STRIP
LENGTH
L Inputs
26-10 AWG 5.31 lb-in (0.6 Nm) to
7.08 lb-in (0.8 Nm) max
3/8” (9 mm)
SW Outputs
26-10 AWG 5.31 lb-in (0.6 Nm) to
7.08 lb-in (0.8 Nm) max
3/8” (9 mm)
Ground Lug 14-4 AWG 25-45 lb-in (2.8-5.1 Nm) 3/4" (19 mm)
Load Wiring for GLXX-SW8 and GLXX-SW16
1. Test the circuit for electrical faults by turning on each circuit breaker, checking that the breakers do not
trip, and that power is delivered to the proper loads.
2. Turn off the circuit breaker(s) and remove all jumpers.
3. Turn on the circuit breakers.