Installation guide
Power Switching Cabinet GLPX-SW-FT Crestron Green Light Express
®
14 • Crestron Green Light Express
®
Power Switching Cabinet GLPX-SW-FT Installation Guide – DOC. 6886B
Wiring
NOTE: All wiring must be installed in accordance with all local and national electrical codes.
NOTE: Refer to the torque settings specified on pages 15 and 16.
Crestron Green Light Express cabinets are shipped with GLXX switching modules installed, refer to “Appendix A:
Specifications” on page 20 for the specifications of the modules. The following must be performed after mounting
the cabinet:
• Connect incoming feed conductors to the L input terminals and connect loads to SW output terminals
(section A of the following diagram)
• Connect control wiring (section B of the following diagram)