Specifications

Table Of Contents
5 - 13
5.9.2 Selective branch/connection
(1) Selective branch
The conditions for multiple transitions (connected in parallel) are judged to
execute only the route for which conditions are established first.
The transition is limited to SHIFT or WAIT.
Example: WAIT
K1
G1
K2
G2
G3
G255
K3 K4
G255
The servo program K1 is started.
Maximum number of selective branches = 255
The conditions for transition
(G1 to G255) are judged after
the start axis is stopped (start
accept flag: OFF) to shift to
the established route.
POINT
(1) The transition conditions are not always judged from left sequentially.
(2) Selective connection
A selective connection is made to connect to one route after selective branching
and processing of each route. It is also possible to set so that the route is not
connected.
END
IFB1
IFE1
Program END
Jump shifting (normal jump)