Specifications

PS2000 Installation Instructions
For more information contact Hubbell Wiring Device Kellems
Toll free (800) 288-6000 or www.hubbell-wiring.com
P a g e | 5
Rev. 4.1--12.12.13
1.3 Electrical wiring requirements and information
PEP Stations require the following:
Two dedicated circuits of single phase 208/240VAC L-L power.
o The left and right circuits must be in phase.
o The L1-L1 and L2-L2 voltage must be equal to 0 volts AC.
Each circuit must be connected to a 40 Amp circuit breaker.
All current carrying conductors between the circuit breaker and the PEP Station must be 8 AWG copper
wires or lower.
All high-voltage wiring must be installed in a 1 ¼” conduit (rigid or PVC).
The CAT5e low-voltage Ethernet cable shall be gel-filled or rated for underground applications, have a
maximum segment length of 100 meters and must installed in a ¾” conduit (rigid or PVC). If using
cellular, there will be an additional 12V power supply wire that will also run in the ¾” conduit from the
PEP Station.
Important:
A centrally located ground must be provided so that the line voltage to central ground does not
exceed 150 Vrms .This type of connection must be used.
Do not provide GFCI protection at the panel, this feature is built-in to the PEP Station.
In areas prone to frequent thunderstorms, install surge protection at the panel for both circuits.
Disconnect the power supply before performing any electrical work.
Label wires from the breaker panel.
The conduit sizes specified above must be maintained within the concrete base and where the
conduit terminates for the wall mounting bracket.