Specifications
PS2000 Installation Instructions
For more information contact Hubbell Wiring Device Kellems
Toll free (800) 288-6000 or www.hubbell-wiring.com
P a g e | 20
Rev. 1.0--
Rev. 4.1—12.12.13
4. Perform a continuity test on the CAT5e Ethernet wire to ensure connectivity before mounting the PEP Station. If
an Internet connection is not available at the time of start-up the station will not become active.
5. Install the electric vehicle parking signage. Two signs per charging station are required, see Figure 24. This sign
can be purchased at www.evsigns.com or by calling the Creative Retail Design Group at (866) 439-6233. Figure
25 is an optional sign for the entrance to the facility parking lot. The signs should be installed at the same height
and in a similar manner to existing handicap signage on the property.
Important: Some cities and municipalities may have standard signage for electric vehicle parking that
will be required. Confirm that the signage specified herein is acceptable; otherwise install the signage
specified by the local jurisdiction.
Important: If connectivity is provided by the WC12000 cellular network a sign will be provided with
the installation kit.
6. Paint parking lot striping and electric vehicle emblems. These colors, emblems and dimensions will most likely
need to be specified by local jurisdiction to maintain consistency with other installations.
7. Verify that the all the items above have been completed and that the site clean and clear of all construction
debris.
Figure 24
Figure 25