Operator`s manual
Installation Procedure
Important!
It is essential that personnel responsible for installing, commissioning and servicing the
machine understand the following:
1. The installation and commissioning of the machine should only be carried out by
trained and authorised service engineers.
2. All water and electrical services must be correctly and safely connected.
3. All covers should be replaced correctly and securely and the machine left in a safe
condition.
4. The machine is suitable for indoor use only, sited in an area with a recommended
ambient temperature not below 10º C and not exceeding 30º C.
5. Prior to moving the machine to its location, ensure that there is sufficient access
space available via passageways, stairs, lifts, etc and that the table/counter where the
machine is to be located is strong enough to safely support its weight. (Refer to
Specifications Table).
6. The machine should be located near the appropriate water and electrical services
as detailed in the specification table.
7. To ensure adequate ventilation, 100 - 150 mm (4 - 6 inches) clearance must be
allowed between the back of the cabinet and the wall.
8. Open the cabinet door. Remove all transit packing and the installation kit from the
machine. Check for visual signs of damage which may have occurred during transit.
9. If the machine is damaged or any parts are missing, you must contact the supplier
immediately.
10. Ensure that the machine is levelled in both front to back and side to side planes
using the adjustable levelling feet.
7
Operator’s Manual