Technical data
Chapter 4 Initial On-grid Testing
24
Chapter 4 Initial On-grid Testing
To ensure operational safety, initial on-grid testing is
required as per the instructions in this chapter before
connecting PV array and grid power after the installation of
CPS SC100KT-O/US-480.
4.1 Testing steps
Conduct the initial on-grid test of CPS
SC100KT-O/US-480 according to the following steps:
(1) Check the appearance of inverter
(2) Check the AC connection
(3) Check the DC connection
(4) Connect to the grid
(5) System self-check and time setup
(6) Set up the operational parameters of AC part
(7) Set up the operational parameters of DC part
(8) Set up the operational parameters of MPPT
(9) Connect to PV
(10) Self-check of power train
(11) Start up the inverter
Note: Please refer to “5.3 Troubleshooting” or contact
our after-sale service personnel if any problem is found
during the testing.
4.2 Testing procedure statement
4.2.1 Appearance of inverter checking
(1) Check whether the inverter has obvious abnormality.