4 VCU Installation and Configuration
This section describes the installation and configuration procedures of the Voasis™ Control Unit
(VCU). These should be performed only after planning the floor coverage and installation
locations as described in section
3.3.
The Voasis™ Single Band Solution VCU kit includes:
Table
4-1: VCU Kit
Description UNIT and P/N
Voasis™
Control Unit
(VCU) kit
Power cord
Voasis™ SW
CD
Local
configuration
cable
(crossed RJ-
45 cable)
4.1 VCU Installation
1. Install the Voasis™ Control Unit (VCU) in the IDF/Telco closet corresponding to the floor to
be covered. The VCU can be installed in the rack or on the wall using the optional wall
mount bracket at the IDF closet along with the provider’s signal source.
2. Connect the VCU to the patch-panel that feeds the existing structured CAT-5/6 cabling
system.
3. Connect (or request the service provider’s service personnel to connect) the provider’s signal
source (pico-cell/micro-cell or BDA) to the RF ports on the VCU, through a passive interface.
4. Apply power to the VCU.
P/N: 255880010
P/N: 705B000101