Infrastructure Requirements and Layout Planning
Voasis™ UMTS/DCS/PCS Installation and Configuration Manual 11
3. After choosing all the jacks to be used, make sure that all the right jacks are connected to
the patch panel at the IDF/telco shaft.
4. It is also recommended to check the area in which the VAPs are about to be installed and
make sure that the installation is feasible.
5. Plan the IDF/telco shaft to hold the RF equipment (pico-cell/micro-cell or BDA) and the VCU.
3.4.3 Installation Plan Example
The Following figure shows a floor plan map with all needed marks:
Figure
3-2. Floor Plan Example
Notes:
The red VAP coverage circles are approximately 30, 40 and 60 foot radius for the small,
medium and large circles respectively (drew according to the guidelines given in section
0).
VAP 3 is surrounded by dense objects, the bathroom and stairwell which would reduce
coverage in that area by the other VAPs.
VAP 5 is an example of a unit that provides good coverage down the hallways.