Table 6: ModuLite™ Installation Labor List
Labor Description Quantity Comment
Installing splice box + splicing
fibers
Installing the box and
opening fibers at MRC.
11
Installing patch panel cabinet +
splicing fibers
Installation of the box and
opening fibers at MBU.
256
Installing Foxcom Wireless
equipment
Installing Modular Base
Units and MRC’s.
36
Installing optic cable
(per 1m)
Pull and install optic cable
through building.
Installing coax cable antennas Install cable antennas on
each floor
Installing electricity ducts (per 1m) Install cables through
ducts in building.
If needed
Installing electricity cables Install cables through
ducts in building.
System checking and report. Trouble shooting and walk