Installation Guide
Litenna
Installation Guide Installation
Foxcom Wireless Proprietary Information Document No. 42-93-005-23D 21
Fiber Installation
The following procedure describes the process for setting up fiberoptic cable for the
system (see Figure 12).
1. Pull fiberoptic cable and DC cable through building structure
2. Install splice tray in 19” rack near Base Unit.
3. Near Base Unit, install patch panel cabinet (SC/APC connectors) for fiberoptic
cable connections.
4. Connect pigtail between splice tray and patch panel cabinet.
5. Connect SC/APC jumpers between the Base Unit and the patch panel.
6. Install splice box near RHU.
7. Connect fiberoptic cable to splice box and pigtails to RHU.