Installation Manual

ote:N If concentric neutral cable is not being used,
follow cable preparation directions in shield
adapter kit.
Equipment provided
DT625 T-body Kit includes:
T-body
Cable Adapter
Shear Bolt Connector
Silicone Lubricant
Instruction Sheet
Tools required
Torque Wrench
5/16” Hex Wrench for Splice Application
Cable Stripping Tools
5 mm or 8 mm Allen Wrench
Installation of connectors
Shear bolt installation procedure
Prepare the cable
Step 1.
Train cable
Position cable vertically so that it is centered between
apparatus bushing and parking pocket, parallel to, and 6”
(152 mm) from apparatus frontplate.
Provide adequate cable slack for cable movement
between standoff bushing and apparatus bushing.
Support cable as needed to maintain position.
Cut cable to length A” from centerline of bushing. (Refer
to Fig ure 3 and Table 1 for A” length.
Figure 3. Line illustration for cable training.
Bushing
Cable
"A"
(See Table 1)
6"
(152 mm)
B
C
D A
Figure 2. Strip back dimensions.
IMPORTANT
Installation Instructions to be used for 600 A, 15 and 25
kV Class DT625 T-body with shear bolt connector. Please
see page 6 for installation instructions using a compression
connector.
2
600 A 15/25 kV class DT625 T-body installation and cable preparation instructions S600-46-2 July 2014 www.cooperpower.com