User guide

© 2013 www.hysecurity.com Page 4
When the concrete has suciently hardened,
remove the templates.
1
2
3
Ensure the posts are plumb.
Shim or grout as required.
Place the Pivot and Catch posts over their respective
conduit and anchor bolt assemblies.
NOTE: Make sure to install the StrongArm M30 Crash Barrier Arm
on a level surface. Both pivot and catch posts must be plumb, level and
on grade with the roadway surface. Slope drainage ¼-inch per foot within 2 feet of the operator.
(2 cm per meter)
4
Secure each anchor plate using the
ten washers and nuts provided for
each post. Torque to 200 ft ∙ lb (271 N∙m)
M30 INSTALL POSTS & GROUND
StrongArm M30 Installation & Assembly - Install Posts & Ground D0432 Rev C
CLEAR OPENING
Pivot Post Catch Post
Hydraulics cover
M30 Arm Saddle
Lower Pivot Mount
(Restraining strap - not shown)
For earth grounding requirements in the U.S.A., refer to the National
Fire Protection Association (NFPA) 780 - Standard for the Installation of
Lightning Protection Systems.
Highlights of the standard include:
e ground rod must be UL listed copper-clad steel, solid copper,
hot-dipped galvanized steel, or stainless steel. Minimum requirements:
½ inch (13 mm) diameter and 8 feet (244 cm) in length.
e ground rod is driven into the earth (refer to local codes for proper
depth requirements).
e ground rod is electrically bonded to the chassis with a single length
of un-spliced 6AWG copper wire less than 3 feet (91cm) long. Due to the
large concrete foundation, make the neccessary adjustments to accomodate
for earth ground requirements.
Local jurisdictions may impose additional or dierent requirements
above the NEC and NFPA 780. Consult the local codes and regulations
regarding requirements in your area.
IMPORTANT: Properly grounding the gate operator is critical to gate
operator performance and the life of its electrical components. Use sucient
wire size during installation. If you do not ground the operator with a separate
earth ground rod, you risk voiding the Limited Warranty.
e potential for lightning discharge exists with all gates, barrier arms,
fences, and gate operators. National Electric Code (NEC) requires a
separate earth ground in addition to the required equipment ground.
DANGER
Pivot Post
Ground rod
6 AWG
M30 Arm Saddle
(Restraining strap - not shown)
Anchor
plate
5
6
Install the grounding rod per local building codes.
Attach a large earth ground wire (6AWG)
from the grounding rod to the lug nut on
the chassis. Feed the 6AWG wire from the
chassis to the earth ground rod.
Anchor plate