Instruction manual
Step 20.5 -Fixing The Base Station To Wall/
Opener
The base station can be attached directly to a sectional 
opener using the M8 bolt and nut supplied. The wire can be 
fed through the top gromet of the opener (Fig. 43)
Note: The bracket may also be rotated so the base station 
hangs above the power head.
Step 20.6 -Installing The Receiver And 
Transmitter
a.  Insert two C-type batteries in the transmitter (Fig. 
44). 
b.  Attach the front cover on the transmitter and secure it 
with four self tapping #6 x 25 screws (supplied).
c.  Attach the mounting bracket to the adjustment bracket 
with one pan head screw M5 x 10. (Fig. 45).
d.  Place the pe bracket on the back of the receiver/
transmitter and secure it with four (M3x5) screws.
e.  Attach the receiver/transmitter to the adjustment 
bracket with one pan head screw M5 x 10.
f.  Mount the receiver to the side of the door closest to 
the base station and transmitter on the other side in 
line with receiver. The mounting surface should be 
rigid. In domestic applications ATA recommends the 
transmitter and receiver are placed in line of sight, 
with the beam 100mm above ground level (as per 
AS60335). This can be achieved by ensuring the 
bottom of the receiver and transmitter are 65mm 
above ground level. They should also be placed as 
close as possible to the door opening (Fig. 46).In 
industrial applications it is recommended that multiple 
Safety Beams are fi tted.
Step 20.7 -Optical Alignment
a.  Make horizontal and/or vertical adjustment on the 
transmitter until the red LED on the receiver stays on, 
this indicates alignment. 
b.  Make horizontal and/or vertical adjustment on the 
receiver until the red LED on the transmitter stays on, 
this indicates alignment. 
c.  Setup the limits of the door opener as per instruction 
manual.
WARNING: When using Safety Beams, the 
doorway must be clear of all obstructions 
and persons at all times. The location of the 
beams and manner in which it is installed 
might not give safety protection at all times. 
Check to make sure that the height of the 
beam and type used give maximum protection 
possible.
65mm
Floor Level
65mm
Mounting Bracket
Mounting Bracket
PE Bracket
Transmitter
+
+
LED
RESET
100mm
Wireless Safety Beams Installation
Fig. 43
Fig. 44
Fig. 45
Fig. 46
Diamond PD Power Drive : Instruction Manual
© Copyright 2012 B&D Doors
23Controll-A-Door
®
 P
Diamond SDO-2v2 Instruction Manual