Operation Manual

13Operation
4 Operation
The Condair RS steam humidier may be commissioned and operated only by persons familiar with the
Condair RS steam humidier and adequately qualied. It is the owner’s responsibility to verify proper
qualication of the personnel.
4.1 First-time commissioning
The rst-time commissioning must always be done by a service technician of your Condair representative
or a well trained and authorised person of the customer. Therefore the current manual does not provide
detailed information on this procedure.
The following steps are carried out upon rst-time commissioning in the specied order:
Inspecting the steam humidier for correct installation.
Inspecting the electrical installation
Inspecting the water installation
Inspecting the steam installation
Flushing the water supply line.
Conguring the control or the Condair RS, respectively.
Carrying out test runs including checking of the control and monitoring devices.
Filling in the commissioning protocol.
4.2 Display and operating elements
Fig. 4: Display and operating elements
DANGER!
Risk of electric shock!
After switching off the unit switch, there is still live voltage inside the control compartment of the Cond-
air RS.Therefore,beforeopeningtheunitthesteamhumidiermustbealwaysseparatedfrom
the mains supplies (heating and control voltage) via the electrical isolators.
1 External electrical isolators for heating and control volt-
age supply (not includ ed in the delivery, must be install-
ed in the mains supply lines)
2 Touchscreen
3 Status LED
green: Condair RS is humidifying
green pulsing: Condair RS is in standby operation
orange: Warning present or maintenance due
red: Fault present
4 Unit switch
Humidier