Technical information

UGH021/0301 VL Series Portable Chillers, 2 to 40 Tons
Page: 25
B. INSTRUMENT OPERATION
1. When the CHILLER ON rocker switch is toggled on, the
instrument will begin temperature control operations and
the to process temperature will begin to drop.
2. When the to process temperature drops 1° below the
setpoint, the instrument will activate the capacity control
system to match the cooling capacity to the present load,
as indicated by the HOT GAS BYPASS light (figure 3.3A).
3. If the load is less than the minimum capacity of the chiller,
the to process temperature will continue to drop. At 3°
below setpoint the compressor will stop and enter a three
minute time delay period before restarting at 1° above
setpoint. The time delay is to prevent short cycling damage
to the compressor.
C. INSTRUMENT CONTROLS
1. CHILLER ON SWITCH: this rocker switch
engages/disengages electrical supply to the compressor and
pump circuit.
2. SELECT: depress to index through the TO PROCESS and
SET POINT temperatures.
3. UP ARROW: depress and hold this push button to increase
the setpoint temperature. If this push button is pressed
momentarily the setpoint value is incremented by one
degree. If the push button is held down for more than one
second, the setpoint will increase slowly at first and then
faster after about two seconds.
4. DOWN ARROW: depress and hold this push button to
decrease the setpoint temperature. If this push button is
pressed momentarily the setpoint value is incremented by
one degree. If the push button is held down for more than
one second, the setpoint will increase slowly at first and
then faster after about two seconds.
D. INSTRUMENT STATUS DISPLAY
1. POWER: illuminates when the proper supply of electrical
power is applied to the unit.
2. PUMP: illuminates when the CHILLER ON rocker switch is
turned on and the pump is operating. Even with the
CHILLER ON rocker switch on, the PUMP light will not
illuminate if a safety fault condition exists.
3. COMPRESSOR: illuminates when the instrument engages