User guide

TrueFeed manual
54
3. Installation
3.1 Mechanical installation
1. If the MV-loader is delivered subsequently instead of together with a TrueFeed, the tube
support needs to be mounted on the frame of the TrueFeed.
2. Install the MV-loader assembly on the TrueFeed. The MV-loader lid fits directly on the hopper
on the TrueFeed. Use the quick release clamps on the TrueFeed hopper to mount the MV-
loader.
3. Connect an ø0.31x0.23 in. {ø8x6 mm} compressed air hose from the compressed air source to
the pressure regulator and from the pressure regulator to Connection 1 on the solenoid valve.
Attach the ø0.31x0.23 in. {ø8x6 mm} compressed air source from Connection 2 of the solenoid
valve to the connection on the top flange of the MV-hopper loader. The ø0.31x0.23 in.
{ø8x6 mm} compressed air source hose must be first connected to the tube support and from
the tube support to the top flange of the MV-hopper loader.
4. Connect the material transfer hose to the inlet connection on the MV-hopper loader and to the
air wand. The material line also needs to be connected to the tube support. Secure the hose
with provided clamps.
IMPORTANT:
Reduce the material transfer hose to the shortest possible length, to avoid wasting
compressed air energy. The material line should be as straight as possible. Avoid
loops and S-curves in flexible hose, this can affect conveying performance.
3.2 Electrical installation
Solenoid valve
The solenoid valve needs to be connected to the control of the TrueFeed. If the hopper loader is
delivered together with a dosing unit, the electrical connection is already made. The wiring
diagram for this connection can be found in this user manual.