Specifications
Chesapeake College Todd Performing Arts Center Auditorium
Audio System Upgrade
March 20
th
, 2015
Audio Systems 27 41 00-10
1. Provide, in writing, within two weeks after award of Contract, the names, mailing
address, phone numbers with extensions, email addresses and paging service numbers
(if available) of the following project personnel:
a. Project Manager
b. Lead Systems Engineer
c. Field Foreman
d. Remote Control System Programmer
G. Conduit Verification
1. Within four weeks after award of Contract, submit statement confirming that Contractor
has reviewed the conduit system as designed in building construction documents and,
where applicable, as built.
2. Notify Consultant, General Contractor, Architect or Electrical Contractor of deficiencies or
inadequacies, if any, in conduit system design or installation. If none, so indicate.
3. Absent conduit verification by Contractor and after installation of conduit as designed,
Contractor shall assume costs of equipment, materials, labor and engineering, including
services of owner’s representative(s) in designing and/or verifying revised wiring
approach(es) as relate to providing a fully functional system using conduit as designed or
as revised at the discretion of the owner.
H. Rigging and Mounting Drawings
1. Submit full size drawings outlining mounting and installation details of all Audio
equipment requiring integration with cabinetry or architectural elements.
2. Details, stamped and signed by an appropriately licensed engineer, of all equipment
mounting methods and materials provided by the Scope of Work, wherein failure of
method or materials used for mounting or hanging permanently installed equipment
could result in serious personal injury.
a. Details provided by or requiring approval by licensed engineer may include: method
of attachment to building structure or attachment and/or suspension points; method
of attachment to supported equipment; all suspension materials; a materials list
including specifications of all suspension materials; calculations used to determine
loads and strengths of suspension materials, other as deemed necessary by the
engineer.
3. In the absence of submitted approved, stamped and signed mounting and hanging
details, the Owner reserves the right to acquire such engineering approval at the
expense of the Contractor. Owner will notify Contractor of such intent. Contractor shall
remedy within two weeks or Owner may proceed without Contractor approval and
without relieving Contractor from any other obligations set forth by Contract.
I. Color Selection
1. Color options for all items as applicable.
2. Wallplate finishes should be coordinated with the Owner.
J. Samples