Step 1-Installing the AC branch circuit junction box
A、Check and make sure the AC voltage is within the voltage range indicated on the label.
B、Mount the Meikai adapter plate at a suitable location on the PV racking system (typically at the
end of a branch of modules).
C、Connect the open wire end of the AC interconnect cable into the junction box using an
appropriate gland or strain relief fitting.
D、Work out the total current basis on the number of micro-inverters in each branch, use an
appropriate cable and connect the AC branch circuit junction box to the point of utility
interconnection.